 September 2006 
Journal
 
Here's a list of September's post-yurt-raising happenings. Photos at bottom.
 
09/15/06 - Friday 
213.02 attach 2x6 T&G flooring 
  
   - relocated boards so work on 20' floor can be done
   
 - time: 3 hrs
  
  
213.26 Platforms: attach perimeter blocking, trim circle, seal cut edges 
  
   - Marked out platform edge on beams
   
 - time: 1 hr
  
  
213.04 attach decking 
  
   - Cass continues...
   
 - time: 3 hrs
  
  
09/16/06 - Saturday 
  
   - Notes
   
 - Mysterious people who apparently cannot read brightly colored No Tresspassing signs decided to amble up the private driveway to YIPPEE-land, stopping by Park Ave to make Cass sick just before she headed up to work on the 20' platform with Chris.  UGH!
  
  
213.26 Platforms: attach perimeter blocking, trim circle, seal cut edges 
  
   - prepped, cut and placed 5 perimeter blocks on 20' platform
   
 - time: 4 hrs
  
  
213.02 attach 2x6 T&G flooring 
  
   - prep work
   
 - 5 rows attached
   
 - time: 2 hrs
  
  
09/17/06 - Sunday 
213.26 Platforms: attach perimeter blocking, trim circle, seal cut edges 
  
   - Cut remaining perimeter blocking
   
 - time: 1.5 hrs
  
  
213.02 attach 2x6 T&G flooring 
  
213.04 attach decking 
  
   - Chris got more boards from the stash
   
 - time: 15 min
  
  
09/18/06 - Monday 
Notes: 
  
   - 15 minutes misc - flooring (tarp) and air out yurt
   
 - nasty humid n bugs
   
 - yurt stinks feel bad but work anyway
  
  
213.04 attach decking 
  
   - skip planing to just get done
   
 - had to add support
   
 - carried one board up
   
 - time: 6 hrs
  
  
09/19/06 - Tuesday 
  
   - Notes
   
 - Woman on radio says, "Enjoy the sunshine."  Huh?!!? 'Tis cloudy humid foggy grey
   
 - rain started shortly after 2:30 and all night
   
 - 15 min opened yurt again and hike back up in rain to close and carried 3 boards up
  
  
213.04 attach decking 
  
09/20/06 - Wednesday 
  
   - Notes
   
 - 15 min open yurt again - ugh awful
  
  
213.04 attach decking 
  
   - carried boads up
   
 - time: 6.75 hrs
  
  
09/21/06 - Thursday 
  
213.04 attach decking 
  
   - finished all can do until boards cut
   
 - time: 3 hrs
  
  
213.27 (MLA/Deck) shape ground for drainage/lay gravel/stone over site 
  
   - sweep underneath and leaves all around
   
 - time: 1hr
  
  
09/22/06 - Friday 
213.02 attach 2x6 T&G flooring 
  
09/23/06 - Saturday 
  
09/24/06 - Sunday 
Notes: more rain 
  
213.15 Raise 20/30' yurts 
  
   - Installed 30' yurt's center ring screen insert, which required a bit of malletting to make it fit
   
 - time: 30 min
  
  
213.27 (MLA/Deck) shape ground for drainage/lay gravel/stone over site 
  
   - Cleaned up yurt raising trash so Cass can get to gravel pile
   
 - time: 30 min
  
  
213.01 Posts + Beams  (Deck) 
  
   - two joists and blocking installed where yurt and deck meet
   
 - Cass whacked head on beam
   
 - time: 3.5 hrs
  
  
09/29/06 - Friday 
  
   - Notes
   
 - rain again
   
 - no site work as Chris shoveled gravel on Oregon Falls Rd with neighbor to fix last years washout damage
   
 - set-up and tested new dryer at house
  
  
09/30/06 - Saturday 
  
   - Notes
   
 - cold, cold..ice on tarp
   
 - Much screwing occurred
  
  
213.02 attach 2x6 T&G flooring 
  
 
 
 Photos 
 
			 |