 March 2006 
Journal
 
Here's a list of March happenings. Photos at bottom.
 
03.04.06 
262.05 Interior walls 
  
   - all but sink-side wall WS and installed
   
 - time: 90m
  
  
03.05.06 
  
   - Water has slowed to a trickle.  Disassembled pipe, no ice in it.  Reservoir is half full. Hmmm.
  
  
03.10.2006 
213.08 Plumbing in Platform 
  
   - Parts hunting
   
 - time: 2.5 hrs
  
  
300.28 Shower arrangements onsite 
  
   - watershielded boards
   
 - design review
   
 - time: 1.5
  
  
03.11.06 
300.28 Shower arrangements onsite 
  
   - watershielded boards
   
 - got parts
   
 - Constructed a big "L" for shower hanging.
   
 - time: 4.5 hrs
  
  
03.12.06 
300.31 Outside area safe for Cass/open windows 
  
   - moved two pallets
   
 - time: 15 m
  
  
03.17.06 
  
   - Buy plumbing supplies
   
 - from VPS
   
 - time: 2 hrs
   
 - Shower on-site
   
 - time: 6 hrs
  
  
03.18.06 
300.31 Outside area safe for Cass/open windows 
  
   - moved two pallets & two boards
   
 - time: 15 min
   
 - shower on-site
   
 - 15 min
   
 - clean ratchet, test katadyn water filter, address shower curtain issue
   
 - Organize shed
   
 - put away plumbing stuff
   
 - time: 1 hr
   
 - PSO!
  
  
03.19.06 
  
   - Weatherstrip Shed
   
 - time: 1 hr
   
 - combination of foil tape and various WS sizes should do the trick.  Doors have the biggest gaps.
  
  
300.28 Shower arrangements onsite 
  
   - cover window opening
   
 - time:  0.25 hr
   
 - note: (and tried pumping filter 1st, approx 3gallons 15mins)
   
 - 3/20/06
  
  
300.28 Shower arrangements onsite 
  
   - make plastic curtain since b+w one  unsafe
   
 - time: 0.25hr
   
 - 3/21/06
  
  
300.28 Shower arrangements onsite 
  
   - working on new design to get gist of it to show chris for specifics, possible?
   
 - Cut off hose length, helped some.
   
 - time: 0.25hr
  
  
03.24.06 
213.08 Plumbing in Platform 
  
   - bought rest of supplies for WC
   
 - time: 1 hr
  
  
300.28 Shower arrangements onsite 
  
   - shopped for parts
   
 - time: 2 hrs
  
  
300.12 Internet Connection 
  
   - time: 1/2 hr to acquire aircard
  
  
03.25.06 
300.31 Outside area safe for Cass/open windows 
  
   - cleaned up remnants of pipe/trenching adventure
   
 - time: 15m
  
  
300.28 Shower arrangements onsite 
  
   - started work on outside structure; ready for test hoisting
   
 - time: 8 hrs
  
  
03.26.06 
300.28 Shower arrangements onsite 
  
   - it lifts and flows
   
 - and it works!
   
 - time: 2h
   
 - note: didn't have enough shots left, fire troubles, rushed it, water not hot enough and poor pressure too.
   
 - 3/27/06
  
  
300.28 Shower arrangements onsite 
  
   - note: sunny but water did not get hot,  or maybe cooled off too much  due to ambient air temps and i waited til after got back from hiking to test. Not being able to go outside w/o shot + illness is an impediment to this situation.
   
 - 3/28/06
  
  
300.28 Shower arrangements onsite 
  
   - note: sunny but water not getting hot.  Post seems to block sun on them when hanging. Try putting on porch to warm. Pressure awful. This is not feasible. :-(
   
 - 3/29/06
  
  
300.28 Shower arrangements onsite 
  
   - note: sunny but water not getting hot. Had them filled and on porch all day.
   
 - 04.01.06
   
 - Internet Connection
   
 - time: 90m
   
 - tried Sierra Wireless card from Unicel on home laptop.  First install seemed okay but Internet Explorer wouldn't connect (and I need a different browser on that machine anyway!)  Called unicel, they had me un/reinstall and no connection happend.  Methi
  
  
 
 